1. | The "Applicant" (Manufacturer) sends a telefax/letter to the ASME Accreditation Department / National Board (NB) to request original "Application Forms" (ASME Fax No: 001 212 591 8599 / NB: 001 614 847 1828) or download it from: | ||||||||||||||||||||||||||||||||||||||||||||||||
2. | Signing of an inspection Service Agreement between the AIA (OneBeacon America Insurance Company / ONE/TÜV/BV) and the "Applicant". | ||||||||||||||||||||||||||||||||||||||||||||||||
3. | Completion of the "Application Forms" indicating the type / scope of certification and stamps applied for and the "AIA" (Authorized Inspection Agency) selected and contracted | ||||||||||||||||||||||||||||||||||||||||||||||||
4. | The completed "Application forms" are returned to the ASME Accreditation Department / National Board by air courier (copy to AIA) / e-mail. | ||||||||||||||||||||||||||||||||||||||||||||||||
5. | Procurement of ASME Code Books, as required per type of certification applied for, with ASME / NB directly | ||||||||||||||||||||||||||||||||||||||||||||||||
6. | ASME notifies the AIA contracted to confirm to ASME that an Inspection Service Agreement has been signed with the "Applicant" | ||||||||||||||||||||||||||||||||||||||||||||||||
7. | The AIA and the "Applicant" establish a Time Schedule for all action to be taken to prepare the Joint Review | ||||||||||||||||||||||||||||||||||||||||||||||||
8. | Scheduling of the Joint Review date with ASME | ||||||||||||||||||||||||||||||||||||||||||||||||
9. | Preparation of the Joint Review:
| ||||||||||||||||||||||||||||||||||||||||||||||||
10. | Implementation of the above-mentioned quality program by the "Applicant" | ||||||||||||||||||||||||||||||||||||||||||||||||
11. | Pre-Joint Review to verify the implementation of the quality program performed by the AI and the AIS approx. 4 weeks before the Joint Review | ||||||||||||||||||||||||||||||||||||||||||||||||
12. | Joint Review with the AIA and ASME | ||||||||||||||||||||||||||||||||||||||||||||||||
13. | ASME issues the certificate(s) and the Code symbol stamp(s) to the "Applicant" | ||||||||||||||||||||||||||||||||||||||||||||||||
14. | The "Applicant" applies to the National Board for the "Certificate of Authorisation for Registration" and the NB-Stamp. This certificate is required to register components built and stamped in compliance with the ASME Code.The registration fee is depending on the size of each item. | ||||||||||||||||||||||||||||||||||||||||||||||||
15. | Receipt of the "Certificate of Authorisation for Registration" and the NB stamp. | ||||||||||||||||||||||||||||||||||||||||||||||||
16. |
|
Rabu, 06 Juli 2011
How to become certified by ASME (Status: Januar 2010)
Langganan: